I. Major
Tasks with Estimated Times to Complete
- A. Upgrade
machine to Echo Speed Capital item (FY budget process) 6 mo-1 yr
- B. Sign research
agreement with GE (allows GE to turn on the fMRI critical protocols) 2-6
mo
- C. Tune System
to fMRI specifications. System may need updated gradient amps, etc. 1.5
mo
- D. Patient
Selection and IRB approval 1-8 mo
- E. Train MR
tech to fMRI protocols 1.5 mo
- F. Purchase
Workstations + Laptop + Color Printer 1 mo
- G. Insure
inbore acoustics/visuals 1-4 mo
- H. Network
connections/cabling 1-6 mo
- I. Purchase
software 1 mo.
- J. Install
software .5 mo
- K. Collect/perform
fMRI data series 1-6 mo
|
|