I. Major Tasks with Estimated Times to Complete

  • A. Upgrade machine to Echo Speed Capital item (FY budget process) 6 mo-1 yr
  • B. Sign research agreement with GE (allows GE to turn on the fMRI critical protocols) 2-6 mo
  • C. Tune System to fMRI specifications. System may need updated gradient amps, etc. 1.5 mo
  • D. Patient Selection and IRB approval 1-8 mo
  • E. Train MR tech to fMRI protocols 1.5 mo
  • F. Purchase Workstations + Laptop + Color Printer 1 mo
  • G. Insure inbore acoustics/visuals 1-4 mo
  • H. Network connections/cabling 1-6 mo
  • I. Purchase software 1 mo.
  • J. Install software .5 mo
  • K. Collect/perform fMRI data series 1-6 mo